Landed · Serangoon Terrace

The ground under it was tendered in 1993. Both ends of that are public; nobody puts them together.

The land under Landed · Serangoon Terrace

HDB put this parcel out to tender and names Landed · Serangoon Terrace as what was built on it. Everything below is from that tender: the dates, the winning price, and the 9 bids that came in.

  1. Tender launched28 Aug 1992
  2. Tender closed23 Oct 19929 bids received
  3. Awarded2 Feb 1993RDC Land Pte Ltd
  4. Winning tenderS$13,980,239HDB publishes no gross floor area for this site, so a rate per square foot cannot be worked out from what is published
Parcel
Serangoon S3f Serangoon Ave 1
Site area
10,829 sq m
Lease
99 yrs
Plot ratio
0.8
Gross floor area
Not published
Sold as
Condominium
Every bid — all 9, as HDB published them
Ranked by amount. The gap column is each bid measured against the winning one — subtraction, not a judgement about whether anyone bid well.
#TendererBidBehind the winner
1RDC Land Pte LtdS$13,980,239—
2Creative Investments Pte LtdS$10,100,000S$3,880,239 · 27.8%
3Lido Development Pte LtdS$8,970,000S$5,010,239 · 35.8%
4DBS Realty Pte LtdS$7,800,000S$6,180,239 · 44.2%
5Union Investment Holding Pte LtdS$7,477,470S$6,502,769 · 46.5%
6Chip Tiong Investment Pte LtdS$7,149,522S$6,830,717 · 48.9%
7Island Tamara Holdings Pte Ltd/Wynyark Investment Pte Ltd/Karimun Shipping Pte LtdS$5,400,000S$8,580,239 · 61.4%
8Melodies LtdS$4,500,000S$9,480,239 · 67.8%
9Golden Development Pte LtdS$2,614,754S$11,365,485 · 81.3%

What the land cost and what a unit sells for are not two ends of one sum. Between them sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold units. None of those is published for a named project, so this site does not estimate a developer’s cost or margin and no figure here should be read as one.

Source: HDB — Sites Sold by HDB · tender awarded 2 Feb 1993 · transcribed from HDB’s published tables on 2026-08-31 · prices are nominal and are not adjusted for inflation. HDB names the development on this row as “Ardisia Gardens”. This parcel, from tender to today · Every land sale

What has been filed there since

1993 · the groundS$13,980,239HDB publishes no gross floor area for this parcel, so no rate can be worked out
Today · the homes on itS$1,618median of 8 filed transactions, 2021-09 to 2026-09

The two ends of this page are not two ends of one sum. Between the tender and the first unit sold sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold stock. None of those is published for a named project, so nothing here estimates a developer’s cost or margin and no figure on this page should be read as one. More on what the site does not publish.