Landed · Jalan Punai

The ground under it was tendered in 1994. Both ends of that are public; nobody puts them together.

The land under Landed · Jalan Punai

HDB put this parcel out to tender and names Landed · Jalan Punai as what was built on it. Everything below is from that tender: the dates, the winning price, and the 6 bids that came in.

  1. Tender launched26 Aug 1994
  2. Tender closed27 Oct 19946 bids received
  3. Awarded9 Dec 1994Habitat Properties Pte Ltd
  4. Winning tenderS$12,000,000HDB publishes no gross floor area for this site, so a rate per square foot cannot be worked out from what is published
Parcel
Bedok S3b Jalan Eunos
Site area
3,345 sq m
Lease
99 yrs
Plot ratio
—
Gross floor area
Not published
Sold as
Condominium
Every bid — all 6, as HDB published them
Ranked by amount. The gap column is each bid measured against the winning one — subtraction, not a judgement about whether anyone bid well.
#TendererBidBehind the winner
1Habitat Properties Pte LtdS$12,000,000—
2LKN Development Pte LtdS$11,700,000S$300,000 · 2.5%
3RDC Land Pte LtdS$10,000,055S$1,999,945 · 16.7%
4Seah Holding Pte LtdS$9,980,000S$2,020,000 · 16.8%
5Tacwealth Investments Pte LtdS$9,732,495S$2,267,505 · 18.9%
6Liang Huat Holding Pte LtdS$8,361,250S$3,638,750 · 30.3%

What the land cost and what a unit sells for are not two ends of one sum. Between them sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold units. None of those is published for a named project, so this site does not estimate a developer’s cost or margin and no figure here should be read as one.

Source: HDB — Sites Sold by HDB · tender awarded 9 Dec 1994 · transcribed from HDB’s published tables on 2026-08-31 · prices are nominal and are not adjusted for inflation. HDB names the development on this row as “Reservoir Villas”. This parcel, from tender to today · Every land sale

What has been filed there since

1994 · the groundS$12,000,000HDB publishes no gross floor area for this parcel, so no rate can be worked out
Today · the homes on itS$1,496median of 6 filed transactions, 2021-09 to 2026-09

The two ends of this page are not two ends of one sum. Between the tender and the first unit sold sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold stock. None of those is published for a named project, so nothing here estimates a developer’s cost or margin and no figure on this page should be read as one. More on what the site does not publish.

The rest of it